Potential Disputes in Government Bank Building Construction Projects in Indonesia

Authors

  • Arjon Arjon INDONESIA
  • Sarwono Hardjomuljadi INDONESIA

DOI:

https://doi.org/10.32832/astonjadro.v13i1.14347

Keywords:

potency dispute; development building; government bank; material; influence.

Abstract

Study This aim For know potency project disputes construction building government bank building in Indonesia. In study This done review systematic library done especially formerly in accordance with specified guidelines. inspection with reading and skimming is done sequentially to identify relevant publications. Analysis References done based on analysis content thematic, for implementation study This method used is correlation regression (research quantitative with questionnaire). Research results This state that inadequate planning and design ripe own very big influence lateness settlement upcoming project cause dispute project and quality poor/deficient work experienced influential big in discrepancy quality upcoming project cause dispute project. Also a factor external related change price and scarcity material raw own influence big reason happening dispute project.

Author Biographies

Arjon Arjon, INDONESIA

Civil Engineering Masters Study Program, Faculty of Engineering, Mercu University Buana, Jakarta

Sarwono Hardjomuljadi, INDONESIA

Civil Engineering Masters Study Program, Faculty of Engineering, Mercu University Buana, Jakarta

References

Abedi, M., M. S. Fathi, dan M. F. Mohammad. 2011. “Major Causes of Construction Delays under Client Category and Contractor Category.” dalam The First Iranian Students Scientific Conference in Malaysia. Malaysia: UPM.

Alaydrus, Ahmad Migdad, dan Sarwono Hardjomuljadi. 2018. “Analisis Faktor Keterlambatan Dimulainya Pelaksanaan Proyek Konstruksi pada Model Kontrak Rancang Bangun.” Jurnal Konstruksia 10(1):95–116.

Ali, Azlan Shah, Andrew Smith, dan Michael Pitt. 2010. “Contractors’ Perception of Factors Contributing to Project Delay: Case Studies of Commercial Projects in Klang Valley, Malaysia.” Journal of Design and Built Environment.

Alifen, Ratna S., Ruben S. Setiawan, dan Andi Sunarto. 1999. “Analisa ‘What If’ Sebagai Metode Antisipasi Keterlambatan Durasi Proyek.” Dimensi Teknik Sipil 1(2):103–13.

Artawan, Aris. 2004. Konstruksi Bangunan Gedung. Bandung: Pustaka Pelajar Offset.

Assaf, Sadi A., Mohammed AI-Khalil, dan Muhammad AI-Hazmi. 1995. “Causes of Delay in Large Building Construction Projects.” Journal of Management in Engineering 11(2):45–50.

Bahemuka, Albert. 2021. “Alternative Dispute Resolution in the Construction Industry: A Case Study of Uganda.” International Journal of Construction Engineering and Management 10(3):80–88. doi: 10.5923/j.ijcem.20211003.03.

Barrie, Donald S., dan Boyd C. Paulson. 2013. Professional Construction Management. 3 ed. McGraw Hill Education.

Braun, Virginia, dan Victoria Clarke. 2006. “Using thematic Analysis in Psychology.” Qualitative Research in Psychology 3(2):77–101. doi: 10.1191/1478088706qp063oa.

Chaphalkar, N. B., K. C. Iyer, dan Smita K. Patil. 2015. “Prediction of Outcome of Construction Dispute Claims Using Multilayer Perceptron Neural Network Model.” International Journal of Project Management 33(8):1827–35. doi: 10.1016/j.ijproman.2015.09.002.

Dipohusodo, Ismawan. 1996. Manajemen Proyek dan Konstruksi ; Jilid 1. Jakarta: Kanisius.

Gamil, Yaser, dan Ismail Abd Rahman. 2022. “Impact of Poor Communication on Dispute Occurrence in The Construction Industry: a Preliminary Exploratory Study of Yemen Construction Industry.” International Journal of Construction Management.

George, C. 2020. “The Essence of Risk Identification in Project Risk Management: An Overview.” International Journal of Science and Research (IJSR) 9(2):1553–57.

Hansen, Seng, dan Susy F. Rostiyanti. 2019. “Indonesian Contractor Professionals’ Perception on Problems in Construction Claim Management.” Malaysian Construction Research Journal 27(1):69–78.

Hardjomuljadi, Sarwono. 2011. “Chance and Desire, The Root of Construction Claims.” Jurnal Konstruksia 2(2):1–15.

Hardjomuljadi, Sarwono. 2014a. “Analisis ‘Extension of Time’ dan Dampaknya pada Kontrak Konstruksi (FIDIC Conditions of Contract MDB Harmonised Edition).” Jurnal Konstruksia 5(2):1–17.

Hardjomuljadi, Sarwono. 2014b. “Factor Analysis on Causal of Construction Claims and Disputes in Indonesia (with Reference to the Construction of Hydroelectric Power Project in Indonesia).” International Journal of Applied Engineering Research 9(22):12421–45.

Hardjomuljadi, Sarwono. 2020. “Use of Dispute Avoidance and Adjudication Boards.” J. Leg. Aff. Dispute Resolut. Eng. Constr 12(4):1–21. doi: 10.1061/(ASCE)LA.1943.

Haseeb, M., Xinhai Lu, Aneesa Bibi, Maloof-ud Dyian, dan Wahab Rabbani. 2012. “PROBLEMS OF PROJECTS AND EFFECTS OF DELAYS IN THE CONSTRUCTION INDUSTRY OF PAKISTAN.” Australian Journal of Business and Management Research 01(06):41–50. doi: 10.52283/nswrca.ajbmr.20110106a05.

Illankoon, I. M. C. S., Vivian W. Y. Tam, Khoa N. Le, dan K. A. T. O. Ranadewa. 2019. “Causes of Disputes, Factors Affecting Dispute Resolution and Effective Alternative Dispute Resolution for Sri Lankan Construction Industry.” International Journal of Construction Management 22(2):218–28. doi: 10.1080/15623599.2019.1616415.

Jaafari, A. 2001. “Management of Risks, Uncertainties and Opportunities on Projects: Time for a Fundamental Shift.” International Journal of Project Management 19:89–101.

Kesai, Panani, Roesdiman Soegiarso, Sarwono Hardjomuljadi, Muhammad Ikhsan Setiawan, Dahlan Abdullah, dan Darmawan Napitupulu. 2018. “Indonesia Position in the Globalization of Construction Industry.” dalam Journal of Physics: Conference Series. Vol. 1114. Institute of Physics Publishing.

Kraiem, Z. I., dan J. E. Dickman. 1987. “Concurrent Delays in Construction Projects.” Journal of Constructions Engineering and Management 113(4):591–602.

Kurniawan, Fredy. 2015. “Jenis Sengketa Yang Sering Terjadi Pada Proyek Konstruksi di Surabaya.” dalam Prosiding Seminar Nasional Teknik Sipil. Surabaya.

Kustiah, Heni, Sarwono Hardjomuljadi, dan Mawardi Amin. 2022. “Faktor Pengaruh Variation Order pada Konstruksi Jalan dan Jembatan untuk Mengurangi Klaim Konstruksi.” Jurnal Konstruksia 13(2):81–92.

Lature, Karolus E. 2018. “Analisis Penyelesaian Sengketa Konstruksi di Indonesia.” Jurnal Legilasi Indonesia 15(3):211–22.

Lindauer, R. 2017. Modern Risk Management Remarks. 1 ed. Bookboon.

Listanto, Nurul, dan Sarwono Hardjomuljadi. 2018. “Analisis Faktor Penyebab Keterlambatan Pembayaran Kontraktor kepada Subkontraktor pada Proyek Gedung Bertingkat.” Jurnal Konstruksia 10(1):59–72.

Madhumitha, L., A. Sivakumar, G. Dhanasekar, dan P. Karthikeyan. 2020. “Identification of Causes of Conflicts and Disputes in Construction Industry.” International Journal of Engineering and Advanced Technology 9(3):1065–71. doi: 10.35940/ijeat.C5154.029320.

Malik, Faisal Iqbal, dan Amanat Ali. 2019. “Investigating the Major Causes and Impacts of Disputes in the Road Construction Projects: A Study of the Selected Projects of Pakistan.” International Journal of Scientific & Engineering Research 10(5).

Newton, P. 2016. Managing a Project Risk: Project Skills. 1 ed. Bookboon.

Nugroho, Rudy, Sarwono Hardjomuljadi, dan Dan Mawardi Amin. 2022. “Dampak Pendemi Covid-19 Atas Timbulnya Klaim Waktu dan Biaya pada Proyek-Proyek Pembangkit Listrik di Indonesia.” Jurnal Konstruksia 14(1):18–23.

Nurmala, Ade, dan Sarwono Hardjomuljadi. 2015. “Penyebab dan Dampak Variation Order (VO) Pada Pelaksanaan Proyek Konstruksi.” Jurnal Konstruksia 6(2):63–77.

Parchami Jalal, Majid, Tayebe Yavari Roushan, Esmatullah Noorzai, dan Maryam Alizadeh. 2020. “A BIM-based Construction Claim Management Model for Early Identification and Visualization of Claims.” Smart and Sustainable Built Environment 10(2):227–57. doi: 10.1108/SASBE-10-2019-0141.

Rachmatullah, Asep, dan Sarwono Hardjomuljadi. 2020. “Analisis Diterimanya Klaim Perpanjangan Waktu dan Tambahan Biaya pada Proyek Bangunan Air di Provinsi Banten.” Jurnal Konstruksia 12(1):1–12.

Rahnamayiezekavat, Payam, Ehsan Sorooshnia, Maria Rashidi, Amir Faraji, Sherif Mostafa, dan Sungkon Moon. 2022. “Forensic Analysis of the Disputes Typology of the NSW Construction Industry Using PLS-SEM and Prospective Trend Analysis.” Buildings 12(10). doi: 10.3390/buildings12101571.

Rudini. 2012. “Pengertian Bangunan Gedung.” Diambil 1 April 2023 (http://rudiniaciel.blogspot.co.id/2012/05/pengertian-bangunangedung.html).

Shahab, Hamid. 1996. Aspek Hukum dalam Sengketa bidang Konstruksi. Jakarta: Djambatan.

Soeharto, Imam. 1999. Manajemen Proyek (Dari Konsep Sampai Operasional). 2 ed. Jakarta: Erlangga.

Taurano, Galih Adya, dan Sarwono Hardjomuljadi. 2013. “Analisis Faktor Penyebab Klaim pada Proyek Konstruksi yang Menggunakan Fidic Conditions of Contract for Plant and Design Build.” Jurnal Konstruksia 5(1):14–25.

Vo, Khoa Dang, Phong Thanh Nguyen, dan Quyen Le Hoang Thuy To Nguyen. 2020. “Disputes in managing projects: A case study of construction industry in Vietnam.” Journal of Asian Finance, Economics and Business 7(8):635–44. doi: 10.13106/JAFEB.2020.VOL7.NO8.635.

Yasin, H. Nazarkhan. 2004. Mengenal Klaim Konstruksi dan Penyelesaian Sengketa Konstruksi. Jakarta: PT. Gramedia Pustaka Utama.

Zhu, Fengfeng, Hao Hu, dan Feng Xu. 2022. “Risk assessment model for international construction projects considering risk interdependence using the DEMATEL method.” PLoS ONE 17(5 May). doi: 10.1371/journal.pone.0265972.

Published

2024-01-08

How to Cite

Arjon, A., & Hardjomuljadi, S. (2024). Potential Disputes in Government Bank Building Construction Projects in Indonesia. ASTONJADRO, 13(1), 48–66. https://doi.org/10.32832/astonjadro.v13i1.14347

Issue

Section

Articles