Analysis of Factors Affecting the Cost Performance of Road Improvement Work in Serang Regency

Authors

  • Tri Gusbian INDONESIA
  • Mawardi Amin INDONESIA

DOI:

https://doi.org/10.32832/astonjadro.v13i1.14732

Keywords:

project; road construction; factor analysis; cost addition; JAPS Version 0.16.2.

Abstract

The Road Infrastructure Development Acceleration Program that has been launched by the Serang Regency Government in the 2017 fiscal year to the 2021 fiscal year, In the implementation of road improvement work in Serang Regency, a working length of 100 kilometers per year has been set for 5 budget years starting from the 2017-2021 fiscal year, the implementation of road improvement work in Serang Regency until the end of 2021 the remaining 20 kilometers due to changes in road length and increase in the volume of work in the field. This study analyzes the factors of additional costs incurred on road improvement work in Serang Regency by identifying the factors causing the cost increase from the largest to smallest factors data collection methods through questionnaires and interviews addressed to contractor personnel with validity, reliability and correlation tests used for data processing, while descriptive analysis is used for data analysis using Jeffreys Amazing Statistics Program (JASP) version 0.16.2 and Relative Importance Index (RII) are expected with this method to determine the factors causing additional costs in road improvement work. The highest level factor was identified as causing the additional cost of implementing Serang Regency road improvement work, namely Volume Changes (Technical Factors) with an RII index value of 0.715.

Author Biographies

Tri Gusbian, INDONESIA

Master of Civil Engineering, Mercu Buana University, Jakarta

Mawardi Amin, INDONESIA

Master of Civil Engineering, Mercu Buana University, Jakarta

References

Atibu Seboru, M. (2015). An Investigation into Factors Causing Delays in Road Construction Projects in Kenya. American Journal of Civil Engineering, 3(3), 51. https://doi.org/10.11648/j.ajce.20150303.11

Damayanti, Y. A., & Sitompul, M. (2021). Analisis Faktor-Faktor yang Mempengaruhi Produktivitas Tenaga Kerja pada Proyek Pembangunan Jalan Tol Ruas Binjai-Langsa Seksi Binjai-Pangkalan Brandan. Jurnal Rekayasa Konstruksi Mekanika Sipil (JRKMS), 04(September), 153–163. https://doi.org/10.54367/jrkms.v4i2.1386

Laksmi, I. A. C. V., Jawat, I. W., & Armaeni, N. K. (2022). Analisis Faktor Yang Berpengaruh Terhadap Pembengkakan Biaya Selama Pelaksanaan Proyek Di Masa Pandemi Covid-19 Pada Pelaku Jasa Konstruksi Skala Kecil Di Bali. FROPIL (Forum Profesional Teknik Sipil), 9(2), 78–85. https://doi.org/10.33019/fropil.v9i2.2432

Lannyati, N., Hardjomuljadi, S., & Amin, M. (2021). One-Sided Contract Dan Pengaruhnya Dalam Hubungan Kerja Di Dunia Konstruksi. Konstruksia, 13, 97–112. https://jurnal.umj.ac.id/index.php/konstruksia/article/view/10385%0Ahttps://jurnal.umj.ac.id/index.php/konstruksia/article/download/10385/6496

Nugroho, R., Hardjomuljadi, S., & Amin, M. (2022). Dampak Pendemi Covid-19 Atas Timbulnya Klaim Waktu Dan Biaya Pada Proyek-Proyek Pembangkit Listrik Di Indonesia. Konstruksia, 14(1), 18. https://doi.org/10.24853/jk.14.1.18-32

Priyo, M., & Sumanto, A. (2016). Analisis Percepatan Waktu Dan Biaya Proyek Konstruksi Dengan Penambahan Jam Kerja (Lembur) Menggunakan Metode Time Cost Trade Off : Studi Kasus Proyek Pembangunan Prasarana. Semesta Teknika, 19(1), 1–15.

Rahmawanto, R., Wicaksono, A., & P. Budio, S. (2014). Faktor-Faktor Penentu Peningkatan Kinerja Pejabat Pembuat Komitmen (Ppk) Pada Satker Apbn Dan Skpd Provinsi Kalimantan Timur. Jurnal Media Teknik Sipil, 10(2), 183–191. https://doi.org/10.22219/jmts.v10i2.1793

Rita, E., Carlo, N., & Nandi. (2022). Penyebab Dan Dampak Keterlambatan Pekerjaan Jalan Di Sumatera Barat Indonesia. Jurnal Rekayasa, 11(1), 27–37. https://doi.org/10.37037/jrftsp.v11i1.94

Rusli, A., & Didi, A. B. (2022). Analisis Faktor-Faktor Penyebab Keterlambatan Kabupaten Enrekang. 2(2), 70–77.

Sahid, M. N., Setiyaningsih, I., Solikhin, M., & Salam, A. (2019). Analisis Faktor-Faktor Penyebab Pembengkakan Biaya Oleh Kontraktor Pada Proyek Jalan Apbd Kota Solo Tahun 2017-2018. Mv, 199–208.

Sumadi, Wayan Edi, Wiranata, A. A., & Asmara, A. A. G. A. (2016). Analisis Faktor Yang Mempengaruhi Pembengkakan Biaya Konstruksi ( Cost Overrun ) Dengan Metode Analytical Heirarchy Process ( Ahp ) Pada Proyek Konstruksi Di Kota Analysis of Factors Affecting the Cost Overrun With Analytical Heirarchy Process Method on C. Ilmiah Teknik Sipil, 20(1), 66–71.

Wirabakti, D. M., Abdullah, R., & Maddeppungeng, A. (2014). Studi Faktor-Faktor Penyebab Keterlambatan Proyek Konstruksi Bangunan Gedung. Teknik Sipil Universitas Agung Tirtayasa, Vol. 6, 15–29.

Akomah, B. B., & Jackson, E. N. (2016). Contractors’ Perception of Factors Contributing to Road Project Delay. International Journal of Construction Engineering and Management, 5(3), 79–85. https://doi.org/10.5923/j.ijcem.20160503.02

Amalia, D. (2019). Analisis Pengaruh Infrastruktur Terhadap Tertumbuhan Ekonomi (Studi Pada 33 Provinsi di Indonesia Tahun 2008–2017). Jurnal Ilmiah Mahasiswa FEB, 1–13.

Anggraini, E. A. (2019). Faktor-Faktor Yang Mempengaruhi Kinerja Biaya Dan Waktu Pada Proyek Konstruksi. Teknika: Jurnal Sains Dan Teknologi, 3(1), 11–22.

Engineering, C., & Sciej, J. (2022). Sultra. 3(1), 9–17.

Muljono, S., Antameng, M., Sinaga, B. M., & Daryanto, A. (2010). DAMPAK PEMBANGUNAN JALAN TERHADAP PENDAPATAN FAKTOR PRODUKSI INTRA DAN INTER REGIONAL KBI-KTI Slamet. Jurnal Transportasi, 10(2), 99–110.

Muluk, M., Misriani, M., Atmaja, J., Ali, S., & Monica, M. (2018). Identifikasi Faktor-Faktor Penyebab Change Order pada Proyek Konstruksi Jalan di Sumatera Barat. Jurnal Ilmiah Rekayasa Sipil, 15(2), 77–87. https://doi.org/10.30630/jirs.15.2.126

Nyoman, I., Astana, Y., Putu, G. A., Dharmayanti, C., Ni, D., & Sumarni, K. (2020). “Strategi Peningkatan Kinerja Pengelolaan Proyek Konstruksi.” Jurnal Spektran, 8(2), 179–186. http://ojs.unud.ac.id/index.php/jsn/index

Rita, E., Carlo, N., & Nandi. (2022). Penyebab Dan Dampak Keterlambatan Pekerjaan Jalan Di Sumatera Barat Indonesia. Jurnal Rekayasa, 11(1), 27–37. https://doi.org/10.37037/jrftsp.v11i1.94

Tenno, Z., & Suroso, A. (2021). Analisis Faktor Penyebab CCO dan Pengaruhnya Terhadap Biaya Kontraktor Pada Proyek Jalan Tol. Jurnal Aplikasi Teknik Sipil, 19(3), 335. https://doi.org/10.12962/j2579-891x.v19i3.9537.

Published

2024-01-13

How to Cite

Gusbian, T., & Amin, M. (2024). Analysis of Factors Affecting the Cost Performance of Road Improvement Work in Serang Regency. ASTONJADRO, 13(1), 251–258. https://doi.org/10.32832/astonjadro.v13i1.14732

Issue

Section

Articles