Analysis of Factors Affecting the Performance of Government Project Completion Time in Pangkalpinang City

Authors

  • Fanta Wahyu Giarta INDONESIA
  • Agus Suroso INDONESIA

DOI:

https://doi.org/10.32832/astonjadro.v14i4.19196

Keywords:

environmental factors, wages, productivity, performance, construction projects.

Abstract

Bangka Belitung Islands Province with its capital city Pangkalpinang has a strategic position as a city located on the economic route of Bangka Island. As an archipelago, it relies heavily on the transportation sector, both land, sea and air transportation to meet construction materials. Astronomically, Pangkalpinang City is located between 2°4’-2°10’ South Latitude and 106°4’-106°7’ East Longitude. Administratively, Pangkalpinang City is divided into 7 sub-districts, namely Bukit Intan, Girimaya, Taman Sari, Gerunggang, Rangkui, Gabek, and Pangkalbalam Districts with a total area of ​​118.41 km2. This research is included in the type of quantitative descriptive research using the survey method. The survey method aims to provide a detailed description of the background, characteristics, and characteristics that are typical of a case or incident of something that is general in nature. The purpose of the study was to obtain solutions to the variables that most influence the performance of the completion time of government building construction in Pangkalpinang City. Based on the results of the T-Test analysis, F-Test and Determination Coefficient Test, it was obtained partially and simultaneously that Environmental Factors (X1), Wage Factors (X2), Coordination (X3), and Worker Productivity (X4) have a significant effect and have a contribution of 85.4% to the performance of the completion time of government building construction projects, 2) based on the results of the variable ranking analysis using multiple linear regression equations & beta coefficient values, it can be concluded that the Wage Factor variable (X2) is the dominant factor that influences the performance of the completion time of building construction projects, which is 72.59%, so to control the completion time of government building construction projects which is mainly carried out by the Project Manager is to control Wages, 3) all research variables, namely Environmental Factors (X1), Labor Factors (X2), Coordination (X3), and Worker Productivity Factors (X4) can affect the performance of the completion time of government building construction projects in Pangkalpinang City. The results of the analysis show that the dominant factor according to all respondents is the labor factor (beta value 1.001).

Author Biographies

Fanta Wahyu Giarta, INDONESIA

Program Studi Magister Teknik Sipil, Universitas Mercu Buana Jakarta

Agus Suroso, INDONESIA

Program Studi Magister Teknik Sipil, Universitas Mercu Buana Jakarta

References

Minister of Public Works and Public Housing of the Republic of Indonesia Number 22/PRT/M/2018

Bakhtiyar, A., Soehardjono, A., & Hasyim, M. H. (2012). Analisis faktor-faktor yang mempengaruhi keterlambatan proyek konstruksi pembangunan gedung di kota lamongan. Rekayasa Sipil, 6(1), 55-66.

BPS Pangkalpinang City, 2023.

Bappeda Pangkalpinang City. 2020.

PMBOK Guide, 2017.

Ervianto, W. I., & MT, I. (2006). Studi Implementasi Teknologi Beton Pracetak Bagi Bangunan Gedung. In National Conference on Prospected Technology.

Apriani, W., Suryanita, R., & Lubis, F. (2020). Evaluasi Kinerja Struktur Jembatan Pelengkung akibat Beban Gempa dengan Analisis Riwayat Waktu. Jurnal Infrastruktur, 6(2), 151-156.

Government Regulation.2010. Number 22 of 2010

Arumningsih. (2012). Perencanaan Dan Estimasi Biaya Pada Proyek Pembangunan Jembatan Patihan Kabupaten Sragen. Jurnal Teknik Sipil dan Arsitektur, 12(16).

Bansambua, E. M. (2019). Faktor-Faktor yang Menyebabkan Keterlambatan Waktu Pelaksanaan Proyek pada Pekerjaan Jalan dan Jembatan di Kabupaten Morowali. Jurnal Maroso, 1(01).

Dharmawan, R. D., Safarizki, H. A., & Firdausi, A. A. Evaluasi Efektivitas Keputusan Addendum Proyek Terhadap Waktu Pekerjaan Proyek Berbasis Earned Value Method. J@ ti Undip: Jurnal Teknik Industri, 18(1), 51-61.

Enrico, Y., & Sumarman, S. (2020). Manajemen Konstruksi pada proyek pembangunan Jembatan untuk akses ke lokasi PT. Pertamina MB-04. Jurnal Konstruksi dan Infrastruktur, 8(1).

Gellysa Urva, & Aminah, S. (2022). Implementasi Metode Analytic Hierarchy Process dalam Pemilihan Proyek Kontruksi. JURNAL UNITEK, 15(2), 141-150. https://doi.org/10.52072/unitek.v15i2.405

Ginting, R., Purba, C. E., & Sinulingga, H. P. (2023). Analisa Manajemen Konstruksi Bangunan Bawah Pada Proyek Pembangunan Jembatan Overpass Ruas Kisaran-Indrapura STA 132+ 023. JURNAL Ilmiah Teknik Sipil, 12(2), 291-296.

Haseli, B., & Hasan Ebdali, E. (2022). Ranking of Project Delay Factors in the Construction of Civil Infrastructure, Case study: Tehran Highway Bridge. New Approaches in Civil Engineering, 5(4), 1-13.

Hai Nguyen, L. (2020). Empirical analysis of a management function’s failures in construction project delay. Journal of Open Innovation: Technology, Market, and Complexity, 6(2), 26.

Sugiyono (2019). Metode Penelitian Kunatitatif Kualitatif dan R&D. Bandung: Alfabeta.

Hair, J. F., Babin, B. J., Anderson, R. E., & Black, W. C. (2022). Multivariate data analysis (8th ed.). London, United Kingdom: Cengage Learning.

Hidayat, A., & Suripto, H. (2019). Klasifikasi Pengendalian Material dalam Mencegah Keterlambatan Proyek di Kabupaten Rokan Hulu. Aptek, 91-96.

Hudoyo, C. P., Rustendi, I., Sismiani, A., & Sunarwono, B. E. (2023). Evaluasi Kinerja Biaya dan Waktu Proyek Konstruksi Jalan dan Jembatan Kawasan Industri Terpadu (KIT) Batang dengan Metode Earned Value. Proceedings Series on Physical & Formal Sciences, 6, 42-47.

Husen, A. (2019). Manajemen Proyek (revisied). Yogyakarta: Cv. Andi Offset. Intan, S. K., Muhyi, A., & Tengku, N. M. (2018). Alternatif Percepatan Waktu Dengan Penerapan Metode Time Cost Trade Off Pada Proyek Pembangunan Jembatan (Studi Kasus: Proyek Pekerjaan Jembatan Rangka Baja Namploh Kec. Samalanga Kab. Bireuen, Aceh). Portal: Jurnal Teknik Sipil, 10(2), 19-27.

Johari, S., & Jha, K. N. (2020). Interrelationship among belief, intention, attitude, behavior, and performance of construction workers. Journal of management in engineering, 36(6), 04020081.

Kala Kamdjoug, J. R. (2023). Change management and digital transformation project success in SMEs located in the Democratic Republic of the Congo. Journal of Enterprise Information Management.

Karthic, Prabakara, Sindhu Vaardini and A. Aswin bharath. Maximizing Real-Time Monitoring For Effective Delay Analysis In Bridge Construction Projects With Evm Scheduling. International Journal of Scientific Research in Engineering and Management (IJSREM). 8(1), DOI: 10.55041/IJSREM27859

Kuswandari, A. D., Koesmargoro, A., & Ervianto, W. I. (2018). Pengaruh Dampak Contract Change Order Terhadap Kinerja Kontraktor Proyek Studi Kasus: Rehabilitasi Jembatan Ngablak. Jurnal Teknik Sipil, 14(4), 255-282.

Larsen, K. R., Michie, S., Hekler, E. B., Gibson, B., Spruijt-Metz, D., Ahern, D., ... & Yi, J. (2017). Behavior change interventions: the potential of ontologies for advancing science and practice. Journal of behavioral medicine, 40, 6- 22.

Mahapatni, I. A. P. S., Putra, C., & Murwanta, K. E. (2022). Analisis Kinerja Waktu dan Biaya Pelaksanaan Proyek dengan Metode Earned Value Pada Proyek Pembangunan Jembatan Pangkung Dalem Ruas Jalan Gitgit- Wanagiri. Jurnal Ilmiah Kurva Teknik, 11(2), 17-25.

Maulina, F., & Mahmuddin, M. (2020). Identifikasi Risiko Pada Proyek Pembangunan Penggantian Jembatan Baja Di Aceh Jaya Dan Aceh Besar. Journal of The Civil Engineering Student, 2(3), 211-217.

Nasution, W. S. I. (2012). Hotel Forest di Bukit Lawang Tema Green Architecture (Doctoral dissertation).

Ramadhan, F. (2021). Evaluasi Penjadwalan Kurva–S Dan Critical Path Method (Cpm) Dalam Mengendalikan Pelaksanaan Pondasi Bore Pile (Studi Pada Pekerjaan Jembatan di Jalan Relokasi Bendungan Tapin) (Doctoral dissertation, Universitas Islam Kalimantan MAB).

Rebut, R., Mangare, J. B., & Walangitan, D. R. (2018). Analisis Perbandingan Tenaga Kerja Lokal Dan Tenaga Kerja Luar Dalam Jasa Konstruksi Di Manado (Studi Kasus: Transmart). Jurnal Sipil Statik, 6(3).

Robbins, Stephen. 2019. Perilaku Organisasi. Edisi Kesepuluh. Jakarta; Indeks.

Sari, A. M. (2021). Faktor Yang Berhubungan Dengan Program Penanggulangan Covid-19 Pada Proyek Jembatan Ploso Jombang Menggunakan Analisis Fishbone. Jurnal Indonesia Sosial Teknologi, 2(09), 1460-1474.

Sugiyono (2019). Metode Penelitian Kunatitatif Kualitatif dan R&D. Bandung: Alfabeta.

Published

2025-12-31

How to Cite

Giarta, F. W., & Suroso, A. (2025). Analysis of Factors Affecting the Performance of Government Project Completion Time in Pangkalpinang City. ASTONJADRO, 14(4), 1196–1220. https://doi.org/10.32832/astonjadro.v14i4.19196

Issue

Section

Articles