Effect of Change Contract Order, Labor, Material, Tools to Time Delayu of Low-Rise State Building Project

Authors

  • Pahala R Tobing INDONESIA
  • Agus Suroso INDONESIA

DOI:

https://doi.org/10.32832/astonjadro.v14i4.19197

Keywords:

Change Contract Order (CCO), man power, material, machine, performance of time, SPSS.

Abstract

Construction of state low-rise buildings in Pangkalpinang city is a common project that usually built by The Public Works Department of Pangkalpinang. The problem often faced by construction of state low-rise buildings projects at Pangkalpinang is the low performance of time (Delay). This condition be expected caused by Change Contract Order (CCO), man power, materials, and machine, This research aims to analyze the influence of those factors on delay time in state low-rise building construction projects. The analysis used in this research is multiple regression with SPSS. This research find that both and parsially the 4 (four) factors influence the time-performance (delay) of low-rise state building construction. Based on data analysis, the equation Y = 3.887+ 0.390 X1 + 0,278 X2 + 0,265 X3 + 0,341 X4. Based on the results of the Coefficient of Determination Test, simultaneously CCO Factors (X1), Manpower Factors (X2), Materials Factors (X3) and Machines Factors (X4) have an influence contribution of 74.0 % of Time Performance (Y). Meanwhile, for the results of the most dominant factor analysis using Beta Standardized x Zero-Order, it was found that the CCO Factor (X2) was the most dominant factor that could influence time performance with an influence value of 23.99%. Considerations in determining alternative solutions to control time performance in state low-rise building construction projects are carried out on the most dominant factor, namely the CCO Factor (X1).

 

Author Biographies

Pahala R Tobing, INDONESIA

Program Studi Magister Teknik Sipil, Universitas Mercu Buana Jakarta

Agus Suroso, INDONESIA

Program Studi Magister Teknik Sipil, Universitas Mercu Buana Jakarta

References

Ervianto, W. I., 2009. Manajemen Proyek Konstruksi. Jakarta: Graha Ilmu.

PMBOK Guide, 2017.

Wulandari, R., Sandi, E.A & Ulfiyati, Y, 2023. Faktor-Faktor Penyebab Keterlambatan Penyelesaian Pembangunan Proyek Suncity Residence, Jurnal Riset Teknik Sipil dan Sains Vol. 1, No. 2, February 2023.

Syah, M.S., 2004. Manajemen Proyek Kiat Sukses Mengelola Proyek, Jakarta: Gramedia.

Haseeb, Lu, Bibi, Dyian and Rabbani. 2011. Problems of Projects and Effects of Delays in the Construction Industry of Pakistan. Australian Journal of Business and Management Research, Vol.1, No.5, p.41-50.

Haseli, B., & Hasan Ebdali, E. (2022). Ranking of Project Delay Factors in the Construction of Civil Infrastructure, Case study: Tehran Highway Bridge. New Approaches in Civil Engineering, 5(4), 1-13.

Amalia, Rohman dan Nurcahyo, 2012. Analisa Penyebab Keterlambatan Proyek Pembangunan Sidoarjo Town Square Menggunakan Metode Fault Tree Analysis (FTA). Jurnal Teknik ITS Vol. 1, No. 1, (Sept. 2012) ISSN: 2301-9271.

Dipohusodo, I., 1996. Manajemen Proyek Dan Konstruksi Jilid II. Jakarta: Kanisius.

Minister of Public Works and Public Housing of the Republic of Indonesia. 2018. No.22/PRT/M/2018 Concerning the Construction of State Buildings in Article 1 paragraph 1 explains the definition of State Buildings

Pangkal Pinang City Regional Regulation. 2014. No.3 of 2014 Concerning Buildings in Article 8 paragraph 8 explains the classification based on the height of buildings

Sugiyono (2019). Metode Penelitian Kunatitatif Kualitatif dan R&D. Bandung: Alfabeta.

Yunisa, S. I. & Puspasari, V. H, 2024. Analisis Faktor-Faktor Penyebab Contract Change Order (CCO) Pada Proyek Konstruksi di Kota Palangka Raya. Jurnal Basement, e-ISSN 2985-9247, Volume 2, No. 2, Agustus 2024, 132-140.

Azwar, 1997. Metode Penelitian Jilid I, Yogyakarta: Pustaka Pelajar.

Ghozali, Imam. 2018. Aplikasi Analisis Multivariate dengan Program IBM SPSS 25. Badan Penerbit Universitas Diponegoro: Semarang.

Hidayat, S. F & Musyafa, A, 2024. Pengaruh Contract Change Order (CCO) Terhadap Kinerja Biaya, Mutu dan Waktu pada Proyek Bangunan Gedung, Jurnal Ilmiah Nusantara (JINU) Vol.1, No. 6 November 2024.

Indramanik, I.G.B, Pagehgiri, J. & Wiguna, A.D.E, 2023. Analisis Faktor-Faktor Yang Mempengaruhi Keterlambatan Waktu Pelaksanaan Proyek Konstruksi Bangunan Fasilitas pariwisata (Studi kasus Kabupaten Badung dan Gianyar). Jurnal Teknik Gradien Vol. 15, No. 01, April 2023.

Nurrizki, F.E, 2024. Analisis Pengaruh Manpower, Machine, Material, Method, Money & Environment Terhadap Kinerja Waktu Pelaksanaan Pembangunan Cold Storage Building. Jakarta: Tesis, Universitas Mercu Buana.

Putra, D.A, Sari, O.L & Situmorang, R, 2023. Factor Analysis of Construction Projects Delay in Balikpapan City. Jurnal Teknik Sipil: Rancang Bangun, Vol. 09 No. 01 April, 2023.

Mamesah, E. A., Walangitan, D.R.O & Arsjad, T.T, 2023. Analisis Faktor – Faktor Penyebab Keterlambatan Proyek Konstruksi Pada Pembangunan Christian Center Tahap II, Jurnal TEKNO, Volume 21, No. 83.

Ariana, I.K.A.,Melinda, R.N., Putri, D.A.P.A.G,, Ariawan, P, 2023. Analisis Pengaruh Perubahan Kontrak (Addendum) Akibat Force Majeure Menggunakan SPSS dan SmartPLS (Studi Kasus: Proyek BKS-LPD Kabupaten Karangasem). Jurnal Teknik Sipil, Volume 19, Nomor 1, April 2023.

Abdullah, Irawan & Riman, 2023. Perbedaan Volume Pelaksanaan Pekerjaan Struktur Terhadap Volume Kontrak Pada Mutual Check 100% dan Cara Mengatasinya pada Proyek Konstruksi (Studi Kasus: Gedung Lapangan Tembak Kedung Cowek Surabaya). Jurnal Ilmiah Teknik Sipil dan Lingkungan Vol. 3 No. 1.

Published

2025-12-31

How to Cite

Tobing, P. R., & Suroso, A. (2025). Effect of Change Contract Order, Labor, Material, Tools to Time Delayu of Low-Rise State Building Project. ASTONJADRO, 14(4), 1221–1243. https://doi.org/10.32832/astonjadro.v14i4.19197

Issue

Section

Articles