Optimization of Contract Change Management and Team Integration in the Critical Center Building Construction Project and Support Services at Dr. Moewardi Regional General Hospital

Authors

  • Hebri Artha Nugroho INDONESIA
  • Absori Absori INDONESIA
  • Mochamad Solikin INDONESIA

DOI:

https://doi.org/10.32832/astonjadro.v15i3.21637

Keywords:

team integration, construction project performance, K-Means Clustering, contract change management, multiple linear regression

Abstract

The increase in the number of patients and the complexity of medical cases at Dr. Moewardi Regional General Hospital has prompted the construction of a Critical Center and Support Services Building as modern facilities for handling critical conditions. However, this type A government hospital project requires effective management of contract changes and coordination between teams across stakeholders. Contract changes in government projects are strictly limited, which has implications for cost efficiency and timeliness. This study was conducted to evaluate the effect of contract change management on time and cost performance, assess the effectiveness of team integration, and formulate concepts for optimizing both. This study was conducted through a quantitative survey of 39 respondents, including project owners, planning consultants, supervisory consultants, and contractors. The survey focused on contract change management indicators and team integration indicators, and was supplemented by project document analysis and in-depth interviews with relevant parties. The results showed a strong influence on overall contract change management (R² = 0.962). K-Means clustering identified three patterns of team integration: positive in cooperation (T5 = 3.21) and responsibility (T8 = 3.31), neutral in mutual trust (T6/T7 = 3.13), and negative in formal communication (T1 = 2.51) and regular meetings (T3 = 2.74). The novelty of this study lies in its integrative approach, which combines regression and clustering simultaneously to analyze and optimize contract management and team integration, with recommendations for strengthening formal communication, BIM, cloud-based platforms, and periodic team evaluations that can be replicated in large-scale health infrastructure projects.

Author Biographies

Hebri Artha Nugroho, INDONESIA

Master of Civil Engineering, Muhammadiyah University of Surakarta

Absori Absori, INDONESIA

Master of Civil Engineering, Muhammadiyah University of Surakarta

Mochamad Solikin, INDONESIA

Master of Civil Engineering, Muhammadiyah University of Surakarta

References

Absori, A., Yulianingrum, A. V., Hasmiati, R. A., & Budiono, A. (2022). Government Policies for the Natural Resource Management of Minerals and Coal Based on Social Welfare. Pena Justisia: Media Komunikasi Dan Kajian Hukum, 20(1), 23–37. https://doi.org/10.31941/pj.v20i1.1715

Baiden, B. K., & Price, A. D. F. (2011). The Impact of Integration on Project Delivery Team Effectiveness. International Journal of Project Management, 29(2), 129–136. https://doi.org/10.1016/j.ijproman.2010.01.016

Budiono, A., Marjanah, I. D., Yuspin, W., Hernanda, T., Absori, A., Bangsawan, M. I., & Ramon, T. M. (2024). Ecoregion-Based Environment Policy to Resolve Water Resource Conflicts at the Surakarta Ex-Residency. WSEAS Transactions on Environment and Development, 20, 491–503. https://doi.org/10.37394/232015.2024.20.48

Dimyati, K., Nashir, H., Elviandri, E., Absori, A., Wardiono, K., & Budiono, A. (2021). Indonesia as a legal welfare state: A prophetic-transcendental basis. Heliyon, 7(8), e07865. https://doi.org/10.1016/j.heliyon.2021.e07865

Hansen, S., & Nindartin, A. (2022). Profiling Contract Change Order Disputes: An Empirical Validation Study. International Journal of Construction Supply Chain Management, 12(2), 16–31. https://doi.org/10.14424/ijcscm120222-16-31

Hartigan, J. A., & Wong, M. A. (1979). Algorithm AS 136: A K-Means Clustering Algorithm. Journal of the Royal Statistical Society. Series C (Applied Statistics), 28(1), 100–108. https://doi.org/10.2307/2346830

Indonesia, R. (2018). Peraturan Presiden Republik Indonesia Nomor 16 Tahun 2018 Tentang Pengadaan Barang/Jasa Pemerintah. Menteri Hukum Dan Hak Asasi Manusia Republik IndonesiPemerintah Republik Indonesia, 22 Maret 2018, 1–90.

Jain, A. K. (2010). Data clustering: 50 years beyond K-means. Pattern Recognition Letters, 31(8), 651–666. https://doi.org/https://doi.org/10.1016/j.patrec.2009.09.011

KPPU. (1999). Draft Pedoman Pasal 5 Tentang Penetapan Harga Uu No . 5 / 1999 Tentang Larangan Praktek Monopoli Dan Persaingan Usaha Tidak. 5, 1–33.

Martanti, A. Y., & Hardjomuljadi, S. (2018). The effect of contract change orders on contractor financing in government projects. International Journal of Civil Engineering and Technology, 9(6), 665–671.

Montgomery, Douglas C. (2012). Introduction to Linear Regression Analysis, 5th Edition. In WILEY SERIES IN PROBABILITY AND STATISTICS Established (Vol. 5, Issue 1).

Nur Sahid, M., Setiyaningsih, I., Solikin, M., & Christianto, J. J. (2019). Kajian Faktor-Faktor Penyebab Cost Overrun Oleh Kontraktor Pada Proyek Jalan Apbd Kabupaten Sukoharjo Tahun 2017 Dan 2018. Jurnal Teknik Sipil, 8(2), 79–88. https://doi.org/10.24815/jts.v8i2.14231

Pramana, A., dkk. (2023). Assessing Ecological and Socio-Economic Attributes in Sustainable Management of Solid Medical Waste in Urban Environment

Sai Kalyan, B. H., Anandh, S., & Sindhu Nachiar, S. (2025). Predicting stakeholder perspectives of alternative dispute resolution in the construction industry using ordinary least squares regression. Organization, Technology and Management in Construction, 17(1), 1–23. https://doi.org/10.2478/otmcj-2025-0001

Sayfuddin. (2022). Study on Factors Affecting the Successful Implementation of Construction Projects in West Lombok District and Mataram City. Journal of Applied Engineering and Technological Science, 3(2), 223–234. https://doi.org/10.37385/jaets.v3i2.825

Sekaran, U., & Bougie, R. (2019). Research Methods for Business: A Skill-Building Approach (6th ed.). John Wiley & Sons

Setiawan, I., & Riantini, L. S. (2021). Risk Evaluation Causes of Contract Change Order to Improve Cost Performance on Railway Construction Project. United International Journal for Research & Technology, 02(09), 2582–6832.

Sugiyono. (2018). Metode Penelitian Bisnis: Pendekatan Kuantitatif, Kualitatif, Kombinasi dan R&D. Bandung: Alfabeta

Sunandar, A., & Aszhari, K. B. (2021). Risk and Change Order Impact Analysis of Costs in the Tamansari Iswara Bekasi Project. Quantitative Economics and Management Studies, 2(4), 261–271. https://doi.org/10.35877/454ri.qems323

Wawak, S., Ljevo, Ž., & Vukomanović, M. (2020). Understanding the Key Quality Factors in Construction Projects—A Systematic Literature Review. In Sustainability (Vol. 12, Issue 24). https://doi.org/10.3390/su122410376

Zulkarnain, Y. P., Djohan, B., & Yulianti, D. (2023). Analisis Pemodelan Pemilihan Moda Transportasi antara Sepeda Motor dengan Angkutan Umum. Jurnal Lateral (Jurnal Teknik Sipil Universitas Tridinanti), Vol. 1 No. 1, 2023.

Published

2026-09-15

How to Cite

Nugroho, H. A., Absori, A., & Solikin, M. (2026). Optimization of Contract Change Management and Team Integration in the Critical Center Building Construction Project and Support Services at Dr. Moewardi Regional General Hospital. ASTONJADRO, 15(3), 812–833. https://doi.org/10.32832/astonjadro.v15i3.21637