Performance Assessment of Construction Projects Using Earned Value Indicators: A Case Study of the Bima Grand Mosque

Authors

  • Rini Pebri Utari INDONESIA
  • Lintang Satiti Mahabella INDONESIA
  • Lourina Evanale Orfa INDONESIA

DOI:

https://doi.org/10.32832/astonjadro.v15i3.22646

Keywords:

construction management, earned value management, project performance, cost control, schedule control.

Abstract

This study evaluates the cost and schedule performance of the Bima Grand Mosque construction project using the Earned Value Management (EVM) method as an comprehensive project control approach. A descriptive quantitative case study was conducted using cumulative project progress data at two critical monitoring points, namely week 55 and week 69. The analysis employed key EVM indicators, including Budgeted Cost of Work Scheduled (BCWS), Budgeted Cost of Work Performed (BCWP), Actual Cost of Work Performed (ACWP), Schedule Variance (SV), Cost Variance (CV), Schedule Performance Index (SPI), and Cost Performance Index (CPI). The results indicate that at week 55 the project was slightly on schedule, with an SPI of 1.001, but experienced cost inefficiency, as reflected by a CPI of 0.990. At week 69, project performance declined, marked by schedule delays and increasing cost overruns, with SPI and CPI values of 0.963 and 0.956, respectively. In addition, the estimated cost at completion increased, accompanied by a slight extension of the projected completion time. The novelty of this study lies in the milestone-based application of EVM to capture dynamic changes in project performance, providing early warning information to support effective cost and schedule control. The findings confirm that EVM is a reliable approach for evaluating construction project performance and facilitating informed managerial decisions.

Author Biographies

Rini Pebri Utari, INDONESIA

Civil Engineering Department, University of Muhammadiyah Malang, Malang

Lintang Satiti Mahabella , INDONESIA

Civil Engineering Department, University of Muhammadiyah Malang, Malang

Lourina Evanale Orfa , INDONESIA

Civil Engineering Department, University of Muhammadiyah Malang, Malang

References

S. Wahyudiono and R. Utari, “Earned Value Management (EVM) Analysis for Maintenance Projects: Insights from GKB 4 at Universitas Muhammadiyah Malang,” Bentang J. Teor. dan Terap. Bid. Rekayasa Sipil, vol. 13, pp. 276–286, Jul. 2025, doi: 10.33558/bentang.v13i2.10632.

R. P. Utari and L. S. Mahabella, “Pengendalian Biaya dan Waktu dengan Pendekatan Metode Earned Value Concept Cost and Time Control with the Earned Value Concept ( EVM ) Method Approach ( Case Study : Class 3 Inpatient Building Development Project Cempaka District Hospital Tabanan-Bali ),” vol. 17, pp. 9–15.

L. Mayo-alvarez, A. Alvarez-risco, S. Del-aguila-arcentales, M. C. Sekar, and A. Y. Jaime, “A Systematic Review of Earned Value Management Methods for Monitoring and Control of Project Schedule Performance : An AHP Approach,” 2022.

R. Widyarso, B. Witjaksana, and J. Purnama, “Analysis Of Time And Cost Performance In Construction Projects Using The Earned Value Management Method,” Asian J. Eng. Soc. Heal., vol. 4, no. 4, pp. 770–779, 2025, doi: 10.46799/ajesh.v4i4.590.

M. B. Febriantoro, S. Susanto, and E. Siswanto, “Meminimalisir Keterlambatan Waktu dan Pembengkakan Biaya Proyek Pembangunan Gedung Kecamatan Dongko, Trenggalek dengan Metode Nilai Hasil (Earned Value Management (EVM)),” vol. 5, 2022.

S. U. Dewi, P. Studi, T. Sipil, U. Sang, and B. Ruwa, “Analisis manajemen waktu dan biaya pada proyek pembangunan gedung menggunakan konsep metode nilai hasil 1,” vol. 04, no. 01, pp. 34–42, 2023.

Q. Fleming and J. Koppelman, Earned Value Project Management, vol. 39. 2000.

A. K. Nica and W. Wody, “Enhancing Facility Management through BIM 6D,” vol. 164, no. June, pp. 299–306, 2016, doi: 10.1016/j.proeng.2016.11.623.

B. Okanlawon, “The Role of Earned Value Management in Enhancing Pipeline Project Scheduling and Performance Tracking Enhancing Pipeline Project Scheduling and,” pp. 0–20, 2025, doi: 10.20944/preprints202509.1208.v1.

D. Przywara and A. Rak, “Monitoring of time and cost variances of schedule using simple Earned Value Management (EVM) indicators,” Appl. Sci., vol. 11, no. 4, pp. 1–13, 2021, doi: 10.3390/app11041357.

R. P. Utari, M. N. Hadad, and S. Wahyudiono, “Analisis Percepatan Proyek dengan Metode Time Cost Trade Off ( Studi Kasus Pada Gedung Student Center UIN Datokrama Palu ) Project Acceleration Analysis with Time Cost Trade Off Method ( A Case Study on the Student Centre Building at UIN Datokrama Palu ),” vol. 20, no. 1, pp. 7–13, 2022.

R. P. Utari, A. Samad, and A. T. Wahono, “Analisis Biaya Konstruksi Menggunakan Metode Life Cycle Cost pada Gedung Cordova Edupartment Semarang Construction Cost Analysis Using the Life Cycle Cost Method in the Cordova Edupartment Building Semarang,” vol. 21, no. 2, pp. 77–83, 2023.

H. Guo, M. Liu, J. Xue, I. Y. Jian, Q. Xu, and Q. Wang, “Post-COVID-19 Recovery : An Integrated Framework of Construction Project Performance Evaluation in China,” 2023.

L. Fan, S. M. Nejad, M. Bagherpour, and M. R. Feylizadeh, “Modeling Sustainable Earned Value Management ( EVM ) Under Grey Uncertain Conditions,” pp. 1–29, 2025.

S. Getahun, R. Ketema, T. Belachew, B. Asteray, D. Samson, and K. Ali, “Performance evaluation of construction project by earned value management system in Amhara waterworks construction enterprise,” Discov. Civ. Eng., 2025, doi: 10.1007/s44290-025-00193-0.

H. R. Putra and W. Oetomo, “Cost and time analysis using methods earned value,” vol. 3, no. 1, pp. 18–33, 2024.

V. V. Engineering, S. A. D. Survey, E. Nejatyan, H. Sarvari, S. A. Hosseini, and H. Javanshir, “Determining the Factors Influencing Construction Project Management Performance Improvement through Earned,” 2023.

V. F. Bahari and M. A. Rizki, “Cost and Schedule Performance Analysis Using the Earned Value Concept in the Construction of the Integrated Lecture Building at the State Shipbuilding Polytechnic of Surabaya [ Analisis Kinerja Biaya dan Waktu Menggunakan Konsep Nilai Hasil Pada Pembangunan Gedung Kuliah Terpadu Politeknik Perkapalan Negeri Surabaya ],” pp. 1–12.

S. D. Gil, G. R. Pacheco, and S. A. D. L. Ríos, “Life-Cycle Cost Assessment in Real Estate Decision-Making Processes : Scope , Limits and Shortages of Current Practices — An Integrative Review,” vol. 2019, 2025.

N. Puspita and Y. Lutfiansyah, “Cost and Time Performance Analysis with Concept of Earned Value (Case Study Jakarta - Cikampek II Elevated Project),” IJIEEB Int. J. Integr. Educ. Eng. Bus. , vol. 3, no. 2, pp. 64–70, 2020, doi: 10.29138/ijieeb.v3i2.1167.

Published

2026-09-16

How to Cite

Utari, R. P., Mahabella , L. S., & Orfa , L. E. (2026). Performance Assessment of Construction Projects Using Earned Value Indicators: A Case Study of the Bima Grand Mosque. ASTONJADRO, 15(3), 1014–1021. https://doi.org/10.32832/astonjadro.v15i3.22646

Issue

Section

Articles