Road Pavement Condition Analysis Using PCI to Determine Maintenance Strategies for Wonogiri Dam Road, Malang

Authors

  • Amalia Rahman INDONESIA
  • Henri Siswanto INDONESIA

DOI:

https://doi.org/10.32832/astonjadro.v15i4.24206

Keywords:

pavement condition index, road pavement, road damage, road maintenance, pavement rehabilitation.

Abstract

Bendungan Wonogiri Road is one of the neighborhood roads in Lowokwaru District, Malang City, which has experienced a decline in pavement conditions due to increased traffic activity. This study aims to analyze the condition of the road pavement and determine the appropriate type of treatment using the Pavement Condition Index (PCI) method. The study was conducted through a field survey on a 500 m long road section divided into five observation segments. The types of damage found included potholes, patches, alligator cracks, and longitudinal cracks. The analysis stage was carried out by calculating the density value, deduct value (DV), total deduct value (TDV), corrected deduct value (CDV), and PCI value for each segment. The results showed that the PCI value on Bendungan Wonogiri Road was in the range of 58–100. The STA 0–100 segment obtained a PCI value of 64, STA 100–200 of 58, STA 200–300 of 59, STA 300–400 of 65, and STA 400–500 of 100. Based on these values, the condition of the road pavement is generally included in the good category. The dominant damage found is potholes and longitudinal cracks with a moderate level of damage. The recommended treatment is road rehabilitation in the damaged segment.

Author Biographies

Amalia Rahman, INDONESIA

Department of Civil Engineering and Planning, Malang State University, Malang

Henri Siswanto, INDONESIA

Department of Civil Engineering and Planning, Malang State University, Malang

References

[1] T. W. As Safa, S. Supiyono, and U. Subagyo, “Analisa Kerusakan Ruas Jalan Raya Deandles Kec. Paciran Kabupaten Lamongan Dengan Metode Pavement Condition Index (Pci),” J. Online Skripsi Manaj. Rekayasa Konstr., vol. 6, no. 1, pp. 249–254, 2025, doi: 10.33795/jos-mrk.v6i1.6213.

[2] Y. D. Subekti and H. T. Tjendani, “Analisis index kerusakan Jalan Rigid Pavement dengan metode Pavement Condition Index (PCI) pada Jalan Lebaksono – Jalan Purwojati Ngoro, Kabupaten Mojokerto,” J. Tek. Ind. Terintegrasi, vol. 7, no. 4, pp. 2502–2510, 2024, doi: 10.31004/jutin.v7i4.37248.

[3] K. D. Fitriani and A. Widayanti, “Penilaian Kerusakan Jalan Menggunakan Pavement Condition Index (PCI) Pada Ruas Jalan Raya Mastrip – Joyoboyo,” J. Media Publ. Terap. Transp., pp. 78–89, 2025, doi: 10.26740/mitrans.v3n1.p78-89.

[4] F. A. Mansouri and M. J. Buckley, “Context-dependent adjustments in executive control of goal-directed behaviour: Contribution of frontal brain areas to conflict-induced behavioural adjustments in primates,” Adv. Neurobiol., vol. 21, pp. 71–83, 2018, doi: 10.1007/978-3-319-94593-4_4.

[5] Carni, W. Sumarno, and Y. Defiana, “Analisis Kerusakan Perkerasan Jalan Dengan Menggunakan Metode Bina Marga Dan Pavement Condition Index (Pci),” J. Ilm. Tek. Sipil, vol. 1, no. 2, pp. 43–57, 2024, doi: 10.25157/jiteks.v1i2.3789.

[6] A. Juhara, D. Andariani, and L. Yunliana, “Evaluasi Fungsional Perkerasan Jalan Dengan Menggunakan Metode Pavement Condition Index (PCI) Studi Kasus Ruas Jalan Cihampelas — Bandung,” J. Tek. Media Pengemb. Ilmu dan Apl. Tek., vol. 10, no. 2, pp. 125–134, 2011, doi: 10.26874/jt.vol10no2.184.

[7] E. Adly, A. Rahmawati, D. Setiawan, S. Dewi, and W. Widodo, “Functional Damage Assessment Visually on the Road Using Pavement Condition Index (PCI),” Proc. 4th Int. Conf. Sustain. Innov. 2020–Technology, Eng. Agric. (ICoSITEA 2020), vol. 199, 2021, doi: 10.2991/aer.k.210204.015.

[8] A. Adritama and D. A. Restuti, “Analysis of Road Damage Using the PCI Method,” J. World Conf., vol. 4, no. 2, 2022.

[9] ASTM International, “ASTM D 6433-07 Standard Practice for Roads and Parking Lots Pavement Condition Index Surveys,” pp. 1–48, 2010.

[10] T. L. Ing and S. Riana, “Analisis Kondisi Permukaan Perkerasan Jalan pada Jalan Lemahneundeut dengan Metode PCI dan RCI,” J. Tek. Sipil, vol. 15, no. 1, pp. 36–45, 2019, doi: 10.28932/jts.v15i1.1854.

[11] E. Mulyati and D. Monika Anggraini, “Klasifikasi Kondisi Perkerasan Jalan Menggunakan Metode Pavement Condition Index (PCI),” J. Konstr., vol. 23, no. 2, 2025, doi: 10.33364/konstruksi/v.23-2.2436.

[12] M. Y. Shahin, Pavement Management for Airports, Roads, and Parking Lots. Chapman & Hall, 1994. [Online]. Available: https://books.google.co.id/books?id=dK8XVI9qMIEC

[13] T. S. P. S. Salonten, “Analisis Kerusakan Jalan Dengan Metode Pavement Condition Index (Pci) (Studi Kasus: Jalan Mahir Mahar, Kota Palangka Raya),” J. Tek. J. Teor. dan Terap. Bid. Keteknikan, no. Vol. 6 No. 1 (2022): Jurnal Teknika: Jurnal Teoritis dan Terapan Bidang Keteknikan, Oktober 2022, pp. 66–73, 2022, [Online]. Available: https://e-journal.upr.ac.id/index.php/JT/article/view/7893/4172

[14] S. Mulyana, A. Zhafirah, and I. Nabila Permata Sari, “Pemetaan Kerusakan Jalan Menggunakan Metode Pavement Condition Index dan Metode Bina Marga,” J. Konstr., vol. 23, no. 2, 2025, doi: 10.33364/konstruksi/v.23-2.2891.

[15] B. Y. D. L. S. C. N. P. M. R. E. Manoppo, “Studi Tingkat Kerusakan Jalan Dan Penanganannya Menggunakan Metode PCI (Pavement Condition Index) (Studi Kasus: Ruas Jalan Airmadidi – Tondano; Sta 3+150 – Sta 6+150),” TEKNO, no. Vol. 22 No. 88 (2024): TEKNO, pp. 1077–1088, 2024, [Online]. Available: https://ejournal.unsrat.ac.id/v3/index.php/tekno/article/view/56357/46767

[16] C. Cawisdi, N. Hidayati, Y. A. Saputro, and Mushthofa, “Analisis Analisis Kerusakan Jalan Menggunakan Metode Pavement Condition Index Pada Ruas Jalan Purwogondo – Teluk,” J. Civ. Eng. Study, vol. 4, no. 02, pp. 111–124, 2024, doi: 10.34001/ces.v4i02.903.

Published

2026-10-28

How to Cite

Rahman, A., & Siswanto, H. (2026). Road Pavement Condition Analysis Using PCI to Determine Maintenance Strategies for Wonogiri Dam Road, Malang. ASTONJADRO, 15(4), 1314–1325. https://doi.org/10.32832/astonjadro.v15i4.24206