Evaluating the Determinant Factors of Construction Project Quality via Multivariate Modeling in Lamongan

Authors

  • Zulkifli Lubis INDONESIA
  • Hendramawat Aski Safarizki INDONESIA
  • Hardian Ningsih INDONESIA

DOI:

https://doi.org/10.32832/astonjadro.v15i4.24760

Keywords:

AHSP, Quality, Time Management, Construction, Regression

Abstract

Infrastructure development serves as a vital catalyst for driving regional economic growth. In Lamongan Regency, ongoing road construction programs aim to elevate infrastructure quality. However, implementation is often hampered by significant obstacles. Common issues such as discrepancies between planning and execution, project delays, suboptimal material usage, and the risky practice of underbidding frequently compromise the durability and standards of construction projects. To address these challenges, Unit Price Analysis (AHSP) emerges as a critical instrument for balancing cost efficiency with high-quality outcomes. This study specifically analyzes how AHSP, contractor pricing, project supervision, contractor experience, material availability, and time management influence the quality of construction projects within the regency. Utilizing a quantitative approach, the research surveyed 171 respondents through Likert-scale questionnaires, semi-structured interviews, and comprehensive documentation. The data were analyzed using multivariate regression, incorporating rigorous validity, reliability, and classical assumption tests. The findings reveal that all studied variables exert a significant simultaneous effect on project quality, supported by a high coefficient of determination of 0.930. These results underscore the necessity of integrated project management. Ultimately, this research provides a strategic model for local authorities to enhance construction standards by harmonizing cost efficiency with disciplined time management.

Author Biographies

Zulkifli Lubis, INDONESIA

Civil Engineering Department, Universitas Narotama, Surabaya

Hendramawat Aski Safarizki, INDONESIA

Civil Engineering Department, Universitas Veteran Bangun Nusantara, Sukoharjo

Hardian Ningsih, INDONESIA

Department of Agribusiness Diploma, Faculty of Vocational School, Universitas Sebelas Maret, Surakarta

References

[1] Irshad R, Mehr-un-Nisa, Ghafoor N. Infrastructure and Economic Growth: Evidence from Lower Middle-Income Countries. J Knowl Econ 2023;14:161–79. https://doi.org/10.1007/s13132-021-00855-1.

[2] OCED. Enhancing Connectivity Through Transport Infrastructure: The Role of Official Development Finance and Private Investment. Paris, France: 2018.

[3] Diskominfo.lamongankab. Kemantapan Jalan Lamongan Per Oktober 2025 Mencapai 59,97 persen 2025.

[4] Khakim A. Pemkab Lamongan targetkan 38 ruas Jamula rampung akhir 2025. Antaranews Jatim 2025. https://jatim.antaranews.com/berita/995141/pemkab-lamongan-targetkan-38-ruas-jamula-rampung-akhir-2025 (accessed January 1, 2026).

[5] Vahedi Nikbakht M, Gheibi M, Montazeri H, Yeganeh Khaksar R, Moezzi R, Vadiee A. Identification and Ranking of Factors Affecting the Delay Risk of High-Rise Construction Projects Using AHP and VIKOR Methods. Infrastructures 2024;9:24. https://doi.org/10.3390/infrastructures9020024.

[6] Memon AH, Memon AQ, Khahro SH, Javed Y. Investigation of Project Delays: Towards a Sustainable Construction Industry. Sustainability 2023;15:1457. https://doi.org/10.3390/su15021457.

[7] Elsherbiny SAM, Gad SAF, Alim AMA. Critical Delay Factors in Construction Projects and Their Proposed Solutions from the Perspective of Total Quality Management. Int J Eng Trends Technol 2024;72:1–8. https://doi.org/10.14445/22315381/IJETT-V72I2P101.

[8] Pangestu RP, Manurung EH, Hutagaol K. Analysis of the Budget Plan for the Construction of Freja House BSD Mass Buildings using the BOW, SNI 2008 & 2021 AHSP Methods. Indones J Appl Ind Sci 2023;2:245–56. https://doi.org/10.55927/esa.v2i2.3492.

[9] Arifin ASR, Jonrinaldi J. Cost Estimation Analysis of Construction Projects on Simple Earthquake-Resistant Houses. CIVED 2024;11:13–9. https://doi.org/10.24036/cived.v11i1.485.

[10] Gunawan E, Anita J. Jurnal Arsitektur Zonasi Construction Supervision Management in Maintaining Quality 2025;8:1.

[11] Lappalainen E, Uusitalo P, Pikas E, Seppänen O, Peltokorpi A, Uusitalo P, et al. Improving Design Quality by Contractor Involvement: An Empirical Study on Effects. Buildings 2022;12:1188. https://doi.org/10.3390/buildings12081188.

[12] Yıldız S, Güneş S, Kıvrak S. Examining the Impact of Material Management Practices on Project Performance in the Construction Industry. Buildings 2024;14:2076. https://doi.org/10.3390/buildings14072076.

[13] Sin CH, Nee TS, Yong LY. Quality Management Challenges In Construction Projects: Investigating Factors, Measures, And The Role Of Material Quality Control. Plan MALAYSIA 2024;22. https://doi.org/10.21837/pm.v22i32.1493.

[14] Halawa S, Kakisina SM, Mendrofa MSD, Gulo H. The Influence Of Time Management On The Quality Of Road Construction Projects In Olayama Village, Huruna District, South Nias Regency. J Ilm METADATA 2026;8:148–57. https://doi.org/10.47652/metadata.v8i2.998.

[15] Fakhrulloh ZA, Triana MI. Optimasi waktu proyek konstruksi dengan penambahan jam kerja menggunakan metode crashing (Studi kasus : Proyek pembangunan gedung pusat terpadu RSUD Sidoarjo). J Tek Ind Terintegrasi 2025;8:112–24. https://doi.org/10.31004/jutin.v8i1.38965.

[16] Sayed M, Abdel-Hamid M, El-Dash K. Improving cost estimation in construction projects. Int J Constr Manag 2023;23:135–43. https://doi.org/10.1080/15623599.2020.1853657.

[17] Feng J, Wang Y, Zhang K. Evaluation of the Quality Supervision System for Construction Projects in China Considering the Quality Behavior Risk Transmission. Symmetry (Basel) 2020;12:1660. https://doi.org/10.3390/sym12101660.

[18] Harahap, I. R., Hasibuan, G. C. R., & Anas, R. (2025). Study of ISO 9001:2015 Quality Management System Implementation in RTG Pad Manufacturing Project at Perawang Port. ASTONJADRO, 14(3), 745–752. https://doi.org/10.32832/astonjadro.v14i3.17922

[19] Prasetyo, A. B., Sembiring, D., & Murtiadi, S. (2026). Evaluation of Quality Management Implementation Using the Process Hierarchy Analysis Method . ASTONJADRO, 15(2), 498–508. https://doi.org/10.32832/astonjadro.v15i2.21362

[20] Salsabila, A., Setyowulan, D., & Arifi, E. (2024). Analysis Value Engineering at Work Apartment Building Wall. ASTONJADRO, 13(1), 245–250. https://doi.org/10.32832/astonjadro.v13i1.14713

Published

2026-10-28

How to Cite

Lubis, Z., Safarizki, H. A., & Ningsih, H. (2026). Evaluating the Determinant Factors of Construction Project Quality via Multivariate Modeling in Lamongan. ASTONJADRO, 15(4), 1335–1343. https://doi.org/10.32832/astonjadro.v15i4.24760

Issue

Section

Articles