Optimization with crashing method and linear programming application on type 36 housing projects

Authors

  • Tsulis Iq'bal Khairul Amar Civil Engineering Department, Universitas Muhammadiyah Surakarta, Sukoharjo http://orcid.org/0000-0003-2439-3323
  • Adi Nurcahyo Mathematical Education Department, Universitas Muhammadiyah Surakarta, Sukoharjo
  • Gilang Jenar Bagaskara Civil Engineering Department, Universitas Muhammadiyah Surakarta, Sukoharjo
  • Arif Safta Wijaya Mathematical Education Department, Universitas Muhammadiyah Surakarta, Sukoharjo

DOI:

https://doi.org/10.32832/astonjadro.v12i1.8436

Keywords:

optimization, project acceleration, crashing method, linear programming method, housing.

Abstract

The growth of housing in Indonesia has been very significant in recent years.   The most found type of house is type 36. One of the areas with high purchasing power for housing is the Kendal Regency, which became the object of this study. Often housing projects experience delays caused by internal and external factors that can interfere with the duration of the initial planning. The effort that can be made to maintain the level of progress of the project is by acceleration. The optimal cost of the project due to the reduction in duration can be completed by acceleration techniques (Crashing) as linear programming models.   In this study, Crashing and Linear Programming methods were chosen to optimize the value of adding costs to accelerate three samples of housing. Housing A, Housing B, and Housing C. The data collected is in the form of RAB, scheduling, and other supporting documents. Linear programming in this study using LINDO software. The plan to accelerate the construction of type 36 housing is carried out using alternative overtime working hours, adding 1, 2 and 4 working hours on critical activities of each project. The optimum time is selected based on the smallest cost slope value from the program crashing calculation. The result is shown that in housing A the most optimal addition was 2 hours of overtime with a total extra cost of Rp.   54,643,600 and a total acceleration of 15 days. In housing B, the optimum value of time and cost is by adding 4 hours of overtime with a total additional cost of Rp.   21,644,140 with a 27-day acceleration. In housing C, the development optimizes by adding 4 hours of overtime at an additional cost of Rp.   74,587,900 with a 29-day acceleration.

Author Biographies

Tsulis Iq'bal Khairul Amar, Civil Engineering Department, Universitas Muhammadiyah Surakarta, Sukoharjo

Civil Engineering Department, Universitas Muhammadiyah Surakarta, Sukoharjo

Adi Nurcahyo, Mathematical Education Department, Universitas Muhammadiyah Surakarta, Sukoharjo

Mathematical Education Department, Universitas Muhammadiyah Surakarta, Sukoharjo

Gilang Jenar Bagaskara, Civil Engineering Department, Universitas Muhammadiyah Surakarta, Sukoharjo

Civil Engineering Department, Universitas Muhammadiyah Surakarta, Sukoharjo

Arif Safta Wijaya, Mathematical Education Department, Universitas Muhammadiyah Surakarta, Sukoharjo

Mathematical Education Department, Universitas Muhammadiyah Surakarta, Sukoharjo

References

Aboelmagd, Y. M. R. (2018). Linear programming applications in construction sites. Alexandria Engineering Journal, 57(4), 4177–4187. https://doi.org/10.1016/j.aej.2018.11.006

Citra, Z., Susetyo, B., & Wibowo, P. D. (2018). Optimasi Kinerja Proyek Dengan Penerapan Metode Crashing Dan Linear Programming. 7(2), 106–113.

Constitutional Court. (2020). Putusan Mahkamah Konstutisi Nomor 91/PUU-XVIII/2020. Mahkamah Konstitusi Republik Indonesia, 1–327. https://www.mkri.id/public/content/persidangan/putusan/putusan_mkri_8240_1637826598.pdf

Durdyev, S., Omarov, M., & Ismail, S. (2017). Causes of delay in residential construction projects in Cambodia. Cogent Engineering, 4(1). https://doi.org/10.1080/23311916.2017.1291117

El-Rayes, K., & Kandil, A. (2005). Time-Cost-Quality Trade-Off Analysis for Highway Construction. Journal of Construction Engineering and Management-Asce - J CONSTR ENG MANAGE-ASCE, 131. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:4(477)

Elsina, K., Mandagi, L. R. J. M., Tarore, H., & Malingkas, G. Y. (2013). Optimasi Biaya Dan Durasi Proyek Menggunakan Program Lindo (Studi Kasus: Pembangunan Dermaga Penyeberangan Salakan Tahap Ii). Jurnal Sipil Statik, 1(4), 226–232.

Ervianto, Wulfram I. (2005). Manajemen Proyek Konstruksi (Edisi 3). Yogyakarta: Andi Offset.

Fachrurrazi, & Husin, S. (2021). Practical crash duration estimation for project schedule activities. Journal of King Saud University - Engineering Sciences, 33(1), 1–14. https://doi.org/https://doi.org/10.1016/j.jksues.2019.09.005

Giri Aspia Ningrum, F., & Hartono, W. (2017). Penerapan Metode Crashing Dalam Percepatan Durasi Proyek Dengan Alternatif Penambahan Jam Lembur Dan Shift Kerja (Studi Kasus: Proyek Pembangunan Hotel Grand Keisha, Yogyakarta).

Haryati, F., Panggabean, E. M., & Wahyuni, S. (2021). Pengembangan Bahan Ajar Mata Kuliah Program Linier Berbantuan Software Lindo. AKSIOMA: Jurnal Program Studi Pendidikan Matematika, 10(4), 2791. https://doi.org/10.24127/ajpm.v10i4.3470

Khalishah, P. V. (2021). Analisis Hubungan Tingkat Suku Bunga Dan Penjualan Properti Pada Sektor Residensial. Jurnal Manajemen Aset Dan Penilaian, 1(1), 23–30.

Laksana, A. W., Prasetyo, H. S., Wibowo, M. A., & Hidayat, A. (2014). Optimalisasi Waktu dan Biaya Proyek dengan Analisa Crash Program (Optimizing Project Time and Cost Using Crash Program Analysis). Jurnal Karya Teknik Sipil, 3(3), 747–759.

Messah, Y. A., Penyebab, K., Pelaksanaan, K., Konstruksi, P., Di, G., Kupang, K., & Messah, Y. A. (2013). Kajian Penyebab Keterlambatan Pelaksanaan Proyek Konstuksi Gedung Di Kota Kupang. In Jurnal Teknik Sipil: Vol. II (Issue 2).

Rahmawati, D., Darmawijoyo, D., & Hapizah, H. (2018). Desain Pembelajaran Materi Fungsi Linier Menggunakan Pemodelan Matematika. AKSIOMA: Jurnal Program Studi Pendidikan Matematika, 7(1), 65. https://doi.org/10.24127/ajpm.v7i1.1311

Sahid, M. N., Mulyono, G. S., Nuryanto, A. S. J., & Abdurrosyid, J. (2020). Evaluasi Pengendalian Waktu dan Produktivitas Tenaga Kerja Pelaksanaan Proyek Pembangunan Gedung Parkir Menggunakan Metode Jaringan Kerja Critical Path Methode (CPM) (Studi Kasus : Gedung Parkir Balai Kota Semarang). Dinamika Teknik Sipil: Majalah Ilmiah Teknik Sipil, 13(2), 71–79. https://doi.org/10.23917/dts.v13i2.13057

Statistik, B. P. (2021). Proporsi rumah tangga dengan status kepemilikan rumah milik dan sewa/kontrak menurut provinsi 2019-2021. https://www.bps.go.id/indicator/29/2018/1/proporsi-rumah-tangga-dengan-status-kepemilikan-rumah-milik-dan-sewa-kontrak-menurut-provinsi.html