Dynamic Modeling of Time Cost Trade Off in Design and Build Projects of High Rise Office Buildings
DOI:
https://doi.org/10.32832/astonjadro.v12i3.9070Keywords:
time cost trade off; dynamic system; office high rise building; shedule performance index; design and buildAbstract
This paper aims to determine the impact of accelerated duration on profit and contingency costs. The method uses the design and build project of a high-rise office building, which begins with an analysis of the actual project schedule, the possibility of accelerating the duration with the assumption of additional working hours for workers and the impact of perceived duration on project costs. Then proceed with System Dynamic (SD) modeling with reference to the Time Cost Trade Off theory and end with a scenario of the relationship between project activity acceleration, profit addition and crashing costs. Project acceleration can improve project performance by considering the effect on profits and contingency costs, with a Schedule Performance Index (SPI) of up to 37.8%, it can increase profits between 4.08% due to reduced indirect costs.
References
Alam, T. (2011). Identifikasi Faktor-Faktor Risiko Proyek Rancang Bangun (Design And Build) Pada PT. XYZ Yang Berpengaruh Terhadap Kinerja Waktu. 251.
Anonymus. (2021). Peraturan Pemerintah Nomor 16 Tahun 2021 Tentang Peraturan Pelaksanaan Undang-Undang Nomor 28 Tahun 2002 Tentang Bangunan Gedung. Peraturan Pemerintah, 087169, 406.
Bank of Indonesia. (2020). Indonesia Economic Report 2020 “Synergy to Build Optimism for Economic Recovery.” Bersinergi Membangun Optimisme Pemulihan Ekonomi, 112. https://www.bi.go.id/id/publikasi/laporan-tahunan/perekonomian/Documents/9_LPI2020.pdf
Barlas, Y. (1997). Structure-oriented Behavior Tests in Model Validation 1. 1996.
Budianto, E. A., & Husin, A. E. (2021). Analisis Optimasi Waktu dan Biaya Dengan Metode Time Cost Trade Off pada Proyek Gudang Amunisi. 19, 305–310.
Build, D., Build, D., Build, D., Build, D., Build, D., Build, D., Build, D., Build, D., Build, D., & Build, D. (2015). Seri Mengenal Pengadaan Jasa Konstruksi Pengadaan Pekerjaan Rancang dan Bangun (Design and Build) Bagian 02 – Kapan Memilih Menggunakan Pekerjaan Rancang dan Bangun (Design and Build) Oleh: Fani Dhuha , ST , M . Sc, Pembina Jasa Konstruksi Ahli Muda. 2–4.
Chritamara, S., Ogunlana, S. O., & Bach, N. L. (2002). System dynamics modeling of design and build construction projects. Construction Innovation, 2(4), 269–295. https://doi.org/10.1191/1471417502ci042oa
DBIA. (2006). Design-build effectiveness study. USDOT - Federal Highway Administration, 1307(January). https://www.fhwa.dot.gov/reports/designbuild/designbuild.pdf
Dewobroto, W. (2021). Kegagalan Konstruksi. The Work of Wiryanto Dewobroto, 1. https://wiryanto.blog/2021/02/25/kegagalan-konstruksi/#more-27641
Forrester, J. W. (1961). Industrial Dynamics. The M.I.T. Press.
Global Construction Disputes Report Collaborating to achieve project excellence. (2020).
Hasanah, K. (2010). Mengembangkan Kemampuan Berpikir Kratif Siswa Sekolah Menengah Atas Melalui Pembelajaran Kontekstual Menekankan Pada Intuisi Matematis.
Hu, C., Wang, J., & Mei, Y. (2021). Uncertain Time-Resource-Cost Trade-Off Models for Construction Project Schedule. KSCE Journal of Civil Engineering, 25(8), 2771–2778. https://doi.org/10.1007/s12205-021-1798-7
Jakarta Office Market Post-pandemic fundamentals remain sound. (2020). June.
Jamal, H. (2017). Types of Infrastructure in Urban and Rural Areas.
Kotir, J. H., Smith, C., Brown, G., Marshall, N., & Johnstone, R. (2016). A system dynamics simulation model for sustainable water resources management and agricultural development in the Volta River Basin, Ghana. Science of the Total Environment, 573, 444–457. https://doi.org/10.1016/j.scitotenv.2016.08.081
Kurniawan, W. (2015). Analisa Metode Time Cost Trade Off Pada Pelaksanaan Proyek Pembangunan Gedung The Samator Surabaya.
Mahapatni, I. A. P. S. (2019). Metode Perencanaan dan Pengendalian Proyek Konstruksi. In UNHI Press.
Mendis, D., Hewage, K. N., & Wrzesniewski, J. (2013). Reduction of construction wastes by improving construction contract management: A multinational evaluation. Waste Management and Research. https://doi.org/10.1177/0734242X13495724
Muhammadi. (2001). Analisis Sistem Dinamis (Lingkungan Hidup,Sosial,Ekonomi, Manajemen). UMJ.
No turning back Turning point or business as usual ? (2021).
Okada, R. C., Simons, A. E., & Sattineni, A. (2017). Owner-Requested Changes in the Design and Construction of Government Healthcare Facilities. Procedia Engineering, 196(June), 592–606. https://doi.org/10.1016/j.proeng.2017.08.047
Pandemic Prompts a Flight to Quality. (2022). March.
Qu, J., Wang, Z., & Du, P. (2021). Comparative Study on the Development Trends of High-rise Buildings Above 200 Meters in China, the USA and the UAE. 10(1), 63–71.
Rajput, P., & Tiwari, S. (2015). A Review of Time Cost Trade-Off in Construction Project. Journal of Construction and Building Materials Engineering, 1(2), 1–13.
Riduwan. (2007). Skala Pengukuran Variabel-variabel Penelitian. In Alfabeta, Bandung.
Schreckengost, C. R. (1985). Dynamics Simulation Model : How Valid Are They ? US Government Printing Office.
Sekaran, U. (2011). Research Methods for Business (Metodologi Penelitian Untuk Bisnis). In Metode Penelitian. https://doi.org/10.1017/CBO9781107415324.004
Simanjuntak, M. R. A., & Dhira, A. (2012). Proses Perancangan Perkantoran di Mega Kuningan. Jurnal Ilmiah Media Engineering, 2(1), 47–62.
Sterman, J. (2000). Business Dynamics, System Thinking and Modeling for a Complex World. http://Lst-Iiep.Iiep-Unesco.Org/Cgi-Bin/Wwwi32.Exe/[In=epidoc1.in]/?T2000=013598/(100), 19.
STRATEGI, PERMASALAHAN DAN SOLUSI. (2016).
Sugiyono. (2008). Metode Penelitian Kuatintatif, Kualitatif dan R&D. In Alfabeta. https://doi.org/2008
Tahun, P. M. P. D. K. R. I. N. 22 T. 2020 T. R. S. K. D. K. (2020). Berita Negara. Menteri Kesehatan Republik Indonesia Peraturan Menteri Kesehatan Republik Indonesia, 69(555).
Timothy, T., & Choandi, M. (2020). Kantor Digital Kreatif Startup. Jurnal Sains, Teknologi, Urban, Perancangan, Arsitektur (Stupa), 1(2), 1519. https://doi.org/10.24912/stupa.v1i2.4517
Toronto, C., & Planning, C. (2020). Toronto Employment Survey 2019 Survey Highlights. February.
Umar, A. A. A. F. C., Ronald, M., & Simanjuntak, A. (2020). Analisis Risiko Metode Konstruksi Design and Build Terhadap Waktu Pelaksanaan Proyek pada Pembangunan Gedung PT ABC. Prosiding Seminar Nasional Teknik Sipil, 2012, 241–249.
UNESCO. (2016). Executive Summary Executive Summary Executive Summary. South African Medical Journal, 101(2003), 16.
UU. (2017). UU 2 TAHUN 2017 Jasa Konstruksi.
Waliulu, Y. E. P. R., & Adi, T. J. W. (2021). A system dynamic thinking for modeling infrastructure project duration acceleration. Procedia Computer Science, 197(2021), 420–427. https://doi.org/10.1016/j.procs.2021.12.181
Hair Jr JF, Hult GTM, Ringle CM, Sarstedt M, Danks NP, Ray S. Partial least squares structural equation modeling (PLS-SEM) using R: A workbook. Springer. 2021. 1–208 p.
Pratama S, Fauzi M, Bahri S, Studi P, Sipil T, Limun K. OPTIMASI BIAYA DAN WAKTU PROYEK KONSTRUKSI DENGAN PENAMBAHAN JAM KERJA ( LEMBUR ) DIBANDINGKAN DENGAN PENAMBAHANTENAGA KERJA MENGGUNAKAN METODE TIME COST. 11:278–88.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2023 ASTONJADRO
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Paper submitted to ASTONJADRO is the sole property of the Astonjadro Journal. Unless the author withdraws the paper because he does not want to be published in this journal. The publication rights are in the journal Astonjadro.ASTONJADRO
LICENSE
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Based on a work at http://ejournal.uika-bogor.ac.id/index.php/ASTONJADRO