Analisis Waktu dan Biaya pada Proyek Pembangunan Pasar Induk Senaken Kabupaten Paser dengan Metode Time Cost Trade Off (TCTO)

Authors

  • Amelia Putri Erfaliani Univeristas Balikpapan
  • Jermianto Dwi Pradika Univeristas Balikpapan
  • Irna Hendriyani Univeristas Balikpapan
  • Reno Pratiwi Univeristas Balikpapan

DOI:

https://doi.org/10.32832/komposit.v8i2.15938

Keywords:

Project Management, Time Cost Trade-Off, Additional Working Hours, Aditional Labor

Abstract

Project management is an effort or activity to planning, leadership, organization and control of company resources to achieve predetermined short-term goals as efficiently and effectively as possible. Optimizing costs and time has many methods that can be used, one of which is often used is Time Cost Trade-Off (TCTO. This method aims to find out how much time and costs are needed to complete the project according to the specified targets. The location of this project is at Senaken Market which is on Jalan Yos Sudarso, Senaken Village, Tanah Grogot District, Paser Regency, East Kalimantan, for Rp. 5.872.872.924,41 and the work duration is 112 days. Alternatives to prevent delays and shorten working time by increasing labor and working hours. From the results of the analysis, it is more effective to increase the number of workers than to increase working hours. The total cost of adding 3 workers is 0.6% less than the total cost of adding 3 hours of work with a work duration of 75 days, 37 days faster than the normal time duration.

References

Chusairi, M. & Suryanto, M. (2015). Studi Optimasi Waktu dan Biaya dengan Metode Time Cost Trade Off pada Proyek Pembangunan Gedung Tipe B SMPN Baru Siwalankerto. Jurnal Rekayasa Teknik Sipil, 2(2), 9-15. https://ejournal.unesa.ac.id/index.php/rekayasa-teknik-sipil/article/view/11827

Ginting, D. F. (2023). Analisa Perbandingan Rencana Anggaran Biaya Pelaksanaan Pekerjaan Perumahan dengan Melakukan Perbandingan Perhitungan Harga Satuan Bahan Berdasarkan Survei Lapangan dengan Permen PUPR Nomor 1 Tahun 2022 (Studi Kasus: Perumahan Citra Wahana III Tanjung Anom). Repositori Universitas HKBP Nommensen. https://repository.uhn.ac.id/handle/123456789/8616

Hendriyani, I., Pratiwi, R., & Qadri, N. (2020). Optimasi Waktu dan Biaya pada Pelaksanaan Proyek Peningkatan Jalan Bina Bakti Kelurahan Gunung Seteleng Kabupaten Penajam Paser Utara dengan Metode Time Cost Trade Off (TCTO): Time and Cost Optimization in The Implementation of the Improvement of the Bina Bakti Road of Gunung Seteleng Kabupaten Penajam Paser Utara with Time Cost Trade Off (TCTO) Method. Jurnal Ilmiah Teknik Sipil TRANSUKMA, 3(1), 65–76. DOI: https://doi.org/10.36277/transukma.v3i1.72

Husen, A. (2009). Manajemen Proyek. Yogyakarta: Andi Offset.

Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling. John Wiley & Sons.

Khabibulloh, M., & Adi, T. J. W. (2022). Optimasi Waktu dan Biaya (Time Cost Trade Off-TCTO) Menggunakan Particle Swarm Optimization (PSO). Jurnal Teknik ITS, 11(3), D146–D153.

Oetomo, W., Priyoto, P., & Uhad, U. (2017). Analisis Waktu dan Biaya dengan Metode Crash Duration pada Keterlambatan Proyek Pembangunan Jembatan Sei Hanyu Kabupaten Kapuas. Media Ilmiah Teknik Sipil, 6(1), 8–22.

Setyorini, A., & Wiharjo, A. K. (2005). Optimasi Waktu dan Biaya dengan Precedence Diagram Method pada Proyek Solo Grand Mall. Skripsi. Jurusan Teknik Sipil Fakultas Teknik Universitas Diponegoro, Semarang. http://eprints.undip.ac.id/34561/

Simatupang, N. (2023). Analisa Percepatan Waktu dengan CPM pada Proyek Pembangunan Gedung Rehabilitasi Ketergantungan Obat/Napza dan Pagar Keliling di RSJ. Prof. Dr. Muhammad Ildrem. Repositori Universitas HKBP Nommensen.

Sujarweni, V. W. (2014). Metodelogi Penelitian. Yogyakarta: Pustaka Baru Perss.

Syah, M. S. (2004). Manajemen Proyek Kiat Sukses Mengelola Proyek. Jakarta: Gramedia Pustaka Utama.

Published

2024-08-01

How to Cite

Erfaliani, A. P., Pradika, J. D., Hendriyani, I., & Pratiwi, R. (2024). Analisis Waktu dan Biaya pada Proyek Pembangunan Pasar Induk Senaken Kabupaten Paser dengan Metode Time Cost Trade Off (TCTO) . Jurnal Komposit: Jurnal Ilmu-Ilmu Teknik Sipil, 8(2), 297–308. https://doi.org/10.32832/komposit.v8i2.15938

Issue

Section

Articles