Faktor Dominan Penghambat Pelaksanaan Proyek pada Industri Konstruksi
DOI:
https://doi.org/10.32832/komposit.v10i1.22557Keywords:
Dominant factors, inhibitors of project implementation, construction industry, construction managementAbstract
The construction sector in Indonesia has experienced significant growth in recent years, marked by frequent project delays across various construction projects. Project delays are a pressing issue in the Indonesian construction industry. Investors are increasingly concerned about this issue, necessitating a comprehensive study to uncover potential solutions. Therefore, a comprehensive study of construction project delays in Indonesia is needed. This study examines in-depth the parties involved in construction project implementation, namely project owners, consultants, and contractors. This study examines twenty (20) main factors causing project delays summarized from several leading journals in previous research from 2024-2016. These inhibiting factors are grouped into three main groups: Owners, Contractors, and Consultants. Literature research in previous journals was conducted to identify the inhibiting factors causing project delays. This analysis ranks project delays to identify the most dominant parties causing construction project delays. The results of this study found that all parties involved have the potential to be inhibitors and causes of delays, thus identifying and assessing the greatest potential causes of project delays. These findings are expected to be a guideline for proposing new strategies in implementing construction projects.
Key words: Dominant Factors, Inhibitors of Project Implementation, Construction Industry
References
Abdulghafour, A. B., & Salman, K. (2023). Delays of construction projects in Makkah from the point of view of the consultant. Journal of Umm Al-Qura University for Engineering and Architecture, 14(2), 122–134. https://doi.org/10.1007/s43995-023-00024-2
Abonassrya, M., Alam, M., & Saifullah, A. (2023). Analysis of Categories That Delay Global Construction Projects. In Lecture Notes in Civil Engineering: Vol. 356 LNCE (Issue August). Springer Nature Singapore. https://doi.org/10.1007/978-981-99-3330-3_15
Akomah, B., Jackson, E. N., & Akomah, B. B. (2016). Contractors’ Perception of Factors Contributing to Road Project Delay. International Journal of Construction Engineering and Management, 5(3), 79–85. https://doi.org/10.5923/j.ijcem.20160503.02
Alrasheed, K., Soliman, E., & Albader, H. (2023). Systematic review of construction project delays in Kuwait. Journal of Engineering Research (Kuwait), 11(4), 347–355. https://doi.org/10.1016/j.jer.2023.08.009
Alshammari, A., & Ghazali, F. E. M. (2024). A Comprehensive Review of the Factors and Strategies to Mitigate Construction Projects Delays in Saudi Arabia. The Open Construction & Building Technology Journal, 18(1), 1–11. https://doi.org/10.2174/0118748368318470240806113627
Amarkhil, Q., Elwakil, E., & Hubbard, B. (2021). A meta-analysis of critical causes of project delay using spearman’s rank and relative importance index integrated approach. Canadian Journal of Civil Engineering, 48(11), 1498–1507. https://doi.org/10.1139/cjce-2020-0527
Aminorlah, A. I., Rahim, N. A., Mohamed, Z., & Mazlan, A. N. (2023). Critical Delay Factors in Typical Physical Projects: The Case of the Ministry of Home Affairs in Malaysia. Journal of Construction in Developing Countries, 28(2), 57–79. https://doi.org/10.21315/JCDC-01-22-0014
Amoatey, C. T., & Ankrah, A. N. O. (2017). Exploring critical road project delay factors in Ghana. Journal of Facilities Management, 15(2), 110–127. https://doi.org/10.1108/JFM-09-2016-0036
Anh, P. X., Nam, T. P., Toan, N. Q., Long, H. D., & Thi, B. V. (2023). Factors affecting the delay of urban development investment projects: A case of Vietnam. International Journal of Innovative Research and Scientific Studies, 6(3), 495–506. https://doi.org/10.53894/ijirss.v6i3.1553
Arumsari, P., & Karim, M. M. (2020). Identification of dominant factors for the delays in building construction project in kepulauan Anambas. IOP Conference Series: Earth and Environmental Science, 426(1). https://doi.org/10.1088/1755-1315/426/1/012040
Asmi, A., Djamaris, A., & Ihsan, M. (2019). Top Ten Similarity Ranking for Project Delay Factors in Construction Industry. IOP Conference Series: Materials Science and Engineering, 650(1). https://doi.org/10.1088/1757-899X/650/1/012006
Ayudhya, B. I. N. (2023). Exploring causes of delay in payment from parties involved in road and highway projects in Thailand. Procedia Computer Science, 219, 1801–1806. https://doi.org/10.1016/j.procs.2023.01.476
Daoud, A. O., El Hefnawy, M., & Wefki, H. (2023). Investigation of critical factors affecting cost overruns and delays in Egyptian megaconstruction projects. Alexandria Engineering Journal, 83(October), 326–334. https://doi.org/10.1016/j.aej.2023.10.052
Braimah, N. (2013). Construction delay analysis techniques-a review of application issues and improvement needs. Buildings, 3(3), 506–531. https://doi.org/10.3390/buildings3030506
Darsa, M. H., & Negash, B. T. (2023). Significant Factors Causing Delay of Ethiopian Road Construction Projects performing by Foreign General Contactors. International Journal of Sustainable Construction Engineering and Technology, 14(4), 103–116. https://doi.org/10.30880/ijscet.2023.14.04.09
Egwim, C. N., Alaka, H., Toriola-Coker, L. O., Balogun, H., Ajayi, S., & Oseghale, R. (2023). Extraction of underlying factors causing construction projects delay in Nigeria. Journal of Engineering, Design and Technology, 21(5), 1323–1342. https://doi.org/10.1108/JEDT-04-2021-0211
Elawi, G. S. A., Algahtany, M., & Kashiwagi, D. (2016). Owners’ Perspective of Factors Contributing to Project Delay: Case Studies of Road and Bridge Projects in Saudi Arabia. Procedia Engineering, 145(480), 1402–1409. https://doi.org/10.1016/j.proeng.2016.04.176
Elshaboury, N., Alaa, H., Al-Sakkaf, A., Alfalah, G., & Abdelkader, E. M. (2021). Prioritizing Delay Causes in the Egyptian Building Construction Projects. World Congress on Civil, Structural, and Environmental Engineering, June. https://doi.org/10.11159/icsect21.lx.103
Elsherbiny, S. A. M., Gad, S. A. F., & Alim, A. M. A. (2024). Critical Delay Factors in Construction Projects and Their Proposed Solutions from the Perspective of Total Quality Management. International Journal of Engineering Trends and Technology, 72(2), 1–8. https://doi.org/10.14445/22315381/IJETT-V72I2P101
Hoque, M. I., Safayet, M. A., Rana, M. J., Bhuiyan, A. Y., & Quraishy, G. S. (2023). Analysis of construction delay for delivering quality project in Bangladesh. International Journal of Building Pathology and Adaptation, 41(2), 401–421. https://doi.org/10.1108/IJBPA-03-2021-0032
Ismaila, U., Jung, W., & Park, C. Y. (2022). Delay Causes and Types in Nigerian Power Construction Projects. Energies, 15(3), 1–16. https://doi.org/10.3390/en15030814
Karimi, H., Sarvari, H., Edwards, D. J., Chan, D. W. M., & Olawumi, T. O. (2024). Deploying Bottleneck Management Strategies for Ameliorating Critical Delays in Building Construction Projects: A Case for Developing Country of Iran. Systems, 12(6). https://doi.org/10.3390/systems12060195
Khair, K., Farouk, H., Mohamed, Z., & Mohammad, R. (2016). Causes and effects of delay factors in road construction projects in Sudan. International Journal of Applied Engineering Research, 11(18), 9526–9533. www.researchgate.ner/publications/308898481
Mahamid, I. (2021). Effects of design quality on delay in residential construction projects. Journal of Sustainable Architecture and Civil Engineering, 28(1), 118–129. https://doi.org/10.5755/j01.sace.28.1.20531
Mejía, G., Sánchez, O., Castañeda, K., & Pellicer, E. (2023). Stakeholders’ issues as a source of project delays: a meta-analy-sis between building and road projects. Revista de La Construccion, 22(1), 51–73. https://doi.org/10.7764/RDLC.22.1.51
Ouansrimeang, S., & Wisaeang, K. (2024). Analyzing the critical delay factors for construction projects in the public sector using relative importance index and machine learning techniques. Journal of Infrastructure, Policy and Development, 8(8), 1–30. https://doi.org/10.24294/jipd.v8i8.6208
Patasik, D., Rahim, I. R., & Hamzah, S. (2022). Comparative Study of Delay Factors in Construction Projects in South Sulawesi (BUMN VS Private). IOP Conference Series: Earth and Environmental Science, 1117(1). https://doi.org/10.1088/1755-1315/1117/1/012019
Project Management Institute. (2008). A guide to the project.
Rachmayanti, W., & Arumsari, P. (2021). Risk factors analysis affecting project time delay in construction projects using CATWOE analysis. IOP Conference Series: Earth and Environmental Science, 794(1). https://doi.org/10.1088/1755-1315/794/1/012010
Rustam, A., Yasin, M. N., Zainuddin, M., Yusoff, K. N., & Kamil, N. A. (2024). A Review on Dominant Factors of Project Manager Competency in Various Implementations for the Construction Industry. IOP Conference Series: Earth and Environmental Science, 1347(1), 012044. https://doi.org/10.1088/1755-1315/1347/1/012044
Saha, S. K., Patil, A., Dwivedi, A., Pamucar, D., & Pillai, A. S. (2023). Analyzing the interactions among delay factors in construction projects: A multi criteria decision analysis. Reports in Mechanical Engineering, 4(1), 241–255. https://doi.org/10.31181/rme040116112023s
Salim, W. N., & Sujana, C. M. (2020). Project delay analysis of highrise building project in Jakarta. IOP Conference Series: Earth and Environmental Science, 426(1). https://doi.org/10.1088/1755-1315/426/1/012051
Samarah, A., & Bekr, G. A. (2016). Causes and Effects of Delay in Public Construction Projects in Jordan. American Journal of Engineering Research (AJER), 5, 87–94.
Sanjaya, I. A., Artana, K. B., & Dinariyana, A. A. B. (2022). Risk Assessment of Delay for CEMS and WHRU Installation Project on Plant Shutdown at Central Processing Gas Gundih. IOP Conference Series: Earth and Environmental Science, 1081(1). https://doi.org/10.1088/1755-1315/1081/1/012007
Sharifzada, H., & Deming, Y. (2024). Construction Project Delay Risk Assessment Based on 4M1E Framework and Afghanistan Situation. Civil Engineering Journal (Iran), 10(1), 100–116. https://doi.org/10.28991/CEJ-2024-010-01-06
Sherif, A., & Abdelalim, A. M. (2022). Delay Analysis Techniques and Claim Assessment in Construction Projects. International Journal of Management and Commerce Innovations, 10(May), 316–325. https://doi.org/10.5281/zenodo.7509156
Shui, S., Rifai, A. I., Pamadi, M., Universitas, P., Batam, I., Ladi, B.-S., Gajah Mada, J., Indah, T., Sekupang, K., & Batam, K. (2023). The Analysis Performance of Project Delays in Pile Foundation Work: A Case Study Batam Island. International Journal of Entrepreneurship and Business Development, 06(01), 172–182.
Siddiqui, M. A. W., & Faheem, M. I. (2021). A Review on Schedule Delays in Infrastructure Projects. International Journal of Innovative Research In Technology, 7(8), 234–243. https://tinyurl.com/siddiqui-maw
Soliman, E., & Alrasheed, K. (2021). Model for construction project delay occurrence (PDO). Journal of Engineering Research (Kuwait), 9(3), 144–167. https://doi.org/10.36909/jer.v9i3B.10211
Susanti, R., Fauziyah, S., & Suwarto, F. (2021). Assessing factors towards construction project delays in Indonesia. IOP Conference Series: Earth and Environmental Science, 700(1). https://doi.org/10.1088/1755-1315/700/1/012064
Suta, M. M., & Prasetia, I. (2024). Analysis of Delay in Implementation of Work on Road Projects in Highways Division of Katingan Regency. Technium: Romanian Journal of Applied Sciences and Technology, 19, 40–49. https://doi.org/10.47577/technium.v19i.10597
Tummalapudi, M., Harper, C. M., Taylor, T. R. B., Waddle, S., & Catchings, R. (2022). Causes, Implications, and Strategies for Project Closeout Delays in Highway Construction. Transportation Research Record, 2676(9), 479–490. https://doi.org/10.1177/03611981221087229
Yilmaz, B. U., & Can, G. (2024). Classification of Delay Factors in the Construction Industry According to Stakeholders and Project Types. International Project and Construction Management Conference (IPCMC2024), June. https://tinyurl.com/rg-yilmaz
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Jurnal Komposit: Jurnal Ilmu-ilmu Teknik Sipil

This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.
Authors who publish with this journal agree to the following terms (Penulis yang mengajukan publikasi artikel telah menyetujui hal berikut):
- Through this publication, the author agree to submit the copyright of article writing to Jurnal Komposit: Jurnal Ilmu-ilmu Teknik Sipil. This copyright submission takes the form of, but is not limited to: reproduction of the article and parts therein, including photographic reproductions; distribution of articles through printed and electronic documents; and translation of articles(Bahwa melalui publikasi ini, hak cipta penulisan artikel diserahkan kepada Jurnal Komposit: Jurnal Ilmu-ilmu Teknik Sipil. Penyerahan hak cipta ini berupa, namun tidak terbatas pada: perbanyakan artikel dan bagian di dalamnya, termasuk reproduksi fotografi; penyebarluasan artikel melalui dokumen cetak dan elektronik; serta penterjemahan artikel).
- The authors agree to the terms of the Copyright Notice, according to Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License., which will apply to this article if and when it is published by Jurnal Komposit: Jurnal Ilmu-ilmu Teknik Sipil. (Para penulis setuju dengan ketentuan Pemberitahuan Hak Cipta, sesuai dengan Lisensi Internasional Creative Commons Attribution-NonCommercial-ShareAlike 4.0., yang akan berlaku untuk artikel ini jika dan ketika diterbitkan oleh Jurnal Komposit: Jurnal Ilmu-ilmu Teknik Sipil).

This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.

.png)